Penjelasan @MYRapidKL Berhubung Masalah Tren Aliran Kelana Jaya @ShahrilMokhtar


Saya percaya pagi tadi, ramai warga kota mengeluh dengan perkhidmatan LRT Kelana Jaya terutama yang menaiki tren ini daripada arah Gombak menuju masuk bandaraya Kuala Lumpur.

Berikut penjelasan oleh pihak RapidKL berhubung kejadian berkenaan.

RapidKL’s Kelana Jaya Line LRT’s operations for the Jelatek - Sri Rampai stretch has to opt for a degraded mode, where the trains are manually driven, following a technical hiccup in the signaling system.

Subsequently, the LRT service along this stretch is slow as the service has to be undertaken under a manual mode. A total of 29 four-car trains were deployed but the service remains slow and the crowd still have to wait longer to enter a train.

The technical hiccup situation arises following an exercise to remove an obsolete part of a signaling system as advised by a signaling system contractor appointed by RapidKL.

The exercise, which started at 12am this morning and supervised by the signaling system contractor, encountered unexpected difficulties at 4:00am which disrupted the Automatic Train Operation System for the line.

Currently, RapidKL engineers are resolving the situation and the system is back to normal at 12:27pm today. RapidKL regrets any inconvenience arising from the situation.


Semoga pengguna yang terkandas dan terlewat memasuki pejabat awal pagi ini dapat menggunakan kenyataan media daripada pihak pengurusan RapidKL.


Follow - @MYRapidKL

Sumber : MyRapidKL